Recording dayworks
Contents |
[edit] Introduction
Daywork is a means by which a contractor is paid for instructed work based on the cost of labour, materials and plant plus a markup for overheads and profit. It is generally used when work cannot be valued in the normal way. For example, daywork might be instructed when there are no comparative rates in a bill of quantities and a pro-rata method of pricing cannot be used. This method of pricing can be open to exploitation, so it is advisable to put monitoring and controlling procedures in place.
[edit] Recording dayworks
Contractors will usually have a template or daywork sheet to capture labour hours, materials and plant. Dayworks can either be, percentage addition or all-inclusive rates. With all-inclusive dayworks a pre-established schedule of rates submitted at tender is used to price the daywork.
A typical daywork sheet might contain the following:
- Project details.
- Instructions issued by the client or site instructions.
- Date (some contractors capture a week's work on a daywork sheet).
- Description of the dayworks.
- Details of labour, including workers' names and hours worked.
- Details of all materials used.
- Details of all plant used.
- Add on costs – profit and overhead.
- Signature area for the contractor’s representative.
- Signature area for the client’s representative.
The client’s team on-site should monitor the daywork. If a clerk of works is part of the client team, monitoring dayworks will typically be their duty. They will verify the hours captured and plant and materials used and sign off the daywork sheet. Their signature will only verify the data captured on-site and not that the daywork sheet is a valid claim for the final account.
[edit] Conclusion
Daywork instructions can be a contentious issue in the industry, and programme pressures can affect the clarity of works instructed. Clear communication between the contractor and the client’s team is vital to minimise disputes, including clear instructions relating to time scales and procedures that must be followed.
[edit] Related articles on Designing Buildings
- Abortive work in building design and construction.
- Architect's instruction.
- Change order for construction contracts.
- Construction contract.
- Change control procedure for building design and construction.
- Compensation event.
- Bill of quantities BOQ.
- Confirmation of verbal instruction.
- Dayworks in construction.
- Payment for extra work.
- Valuation.
- Valuation of interim payments.
Featured articles and news
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.
The Remarkable Pinwill Sisters: from ‘lady woodcarvers’ to professionals. Book review.
Skills gap and investment returns on apprenticeships
ECA welcomes new reports from JTL Training and The Electrotechnical Skills Partnership.
Committee report criticises UK retrofit schemes
CIOB responds to UK’s Energy Security and Net Zero Committee report.
Design and construction industry podcasts
Professional development, practice, the pandemic, platforms and podcasts. Have we missed anything?
C20 Society; Buildings at Risk List 2025
10 more buildings published with updates on the past decade of buildings featured.
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation, closing 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
From project managers to rising stars, sustainability pioneers and more.
Places of Worship in Britain and Ireland, 1929-1990. Book review.