Recording dayworks
Contents |
[edit] Introduction
Daywork is a means by which a contractor is paid for instructed work based on the cost of labour, materials and plant plus a markup for overheads and profit. It is generally used when work cannot be valued in the normal way. For example, daywork might be instructed when there are no comparative rates in a bill of quantities and a pro-rata method of pricing cannot be used. This method of pricing can be open to exploitation, so it is advisable to put monitoring and controlling procedures in place.
[edit] Recording dayworks
Contractors will usually have a template or daywork sheet to capture labour hours, materials and plant. Dayworks can either be, percentage addition or all-inclusive rates. With all-inclusive dayworks a pre-established schedule of rates submitted at tender is used to price the daywork.
A typical daywork sheet might contain the following:
- Project details.
- Instructions issued by the client or site instructions.
- Date (some contractors capture a week's work on a daywork sheet).
- Description of the dayworks.
- Details of labour, including workers' names and hours worked.
- Details of all materials used.
- Details of all plant used.
- Add on costs – profit and overhead.
- Signature area for the contractor’s representative.
- Signature area for the client’s representative.
The client’s team on-site should monitor the daywork. If a clerk of works is part of the client team, monitoring dayworks will typically be their duty. They will verify the hours captured and plant and materials used and sign off the daywork sheet. Their signature will only verify the data captured on-site and not that the daywork sheet is a valid claim for the final account.
[edit] Conclusion
Daywork instructions can be a contentious issue in the industry, and programme pressures can affect the clarity of works instructed. Clear communication between the contractor and the client’s team is vital to minimise disputes, including clear instructions relating to time scales and procedures that must be followed.
[edit] Related articles on Designing Buildings
- Abortive work in building design and construction.
- Architect's instruction.
- Change order for construction contracts.
- Construction contract.
- Change control procedure for building design and construction.
- Compensation event.
- Bill of quantities BOQ.
- Confirmation of verbal instruction.
- Dayworks in construction.
- Payment for extra work.
- Valuation.
- Valuation of interim payments.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Sir Edwin Lutyens: Britain's greatest architect? Book review.
CIOB publishes free template to help assess and manage risks.
ECA's reflections on Party Conference season
Burnham wants to be confident of winning before asking for a fresh mandate.
New Chief Construction and Scientific Adviser
Sergio Cavalaro, Professor of Infrastructure Systems at Loughborough University.
Building safety levy for England
CIAT publish estimator tool for members.
Water sector faces a growing crisis that could slow the delivery of vital infrastructure.
Undervaluing our industrial past
Heritage value changes as taste for building styles changes.
Changing expectations around competence and compliance
New information sheet from CIAT.
Grenfell investigation files passed to CPS
Angela Rayner apologises on behalf of the British state.
Electrical contractors need to understand the practical implications.
The real barrier to getting more value from digital technology.
Your guide to The Construction Reset at UKCW Birmingham.